According to her, the impact is felt across multiple government levels, with delayed spending leading to rushed and inefficient project implementation...
According to Auditor-General Nancy Gathungu, only Sh13.4 billion of the approximately Sh60 billion accrued to the fund over 13 years has been released...
The MPs argue that the hospital, intended to provide specialised healthcare for officers and their families, should not be left to waste while the gov...
A total of Sh4.4 billion was paid as interest due to delayed payments, which Gathungu said was an “unnecessary cost” that could have been avoided had...
The Sh21 billion Kibwezi-Mtomo-Kitui-Migwani road project, which is being implemented by KeNHA and financed by Exim Bank, attracted Sh614.2 million in...
Gathungu says the government has already paid Sh7.8 billion for these projects, some of which are now accruing penalties due to delayed payment of cer...
These delays leave thousands of Kenyans, including internally displaced persons (IDPs), squatters, and families living in extreme poverty, in a state...
The audit has painted a troubling picture of poor planning, lax oversight, and disregard for public funds, with stalled and delayed projects affecting...
A report by the National Assembly’s Public Investment Committee has detailed how contracts worth hundreds of millions of shillings were awarded withou...
MPs have expressed outrage over reports from Auditor General Nancy Gathungu’s office that have painted them in a negative light, accusing them of mish...
The railways agency is embroiled in a tussle with the Kenya Urban Roads Authority (Kura) over the improvement of Nairobi Lot 2, which entails the upgr...
This comes even as President William Ruto continues to launch new market initiatives, including recent projects in Nyandarua and Laikipia counties, ra...
The audit reveals that these cancellations, which largely took place towards the end of the financial year in June 2024, are partly due to delayed dis...
Roads Principal Secretary Joseph Mbugua told the committee that the law gives the National Treasury Cabinet Secretary powers to declare a surplus and...
According to the Auditor General, Nancy Gathungu, construction began in February 2013, with the initial completion date set for March 3, 2016. But due...
The audit report by Auditor General Nancy Gathungu had exposed alarming financial irregularities at the Women Enterprise Fund, totalling Sh1.4 billion...
Given the mounting losses, lack of accountability, and failure to comply with government directives, the Women Enterprise Fund’s future remains uncert...
The audit notes that counties were expected to contribute a combined Sh450 million for the 2023/24 financial year, but 12 counties did not provide Sh1...
Omtatah claimed that the Auditor General’s office is not fulfilling its role of auditing for lawfulness and effectiveness, particularly regarding the...
Attempts by the contractor to have the Department of Defence, which supervised the construction until the 2022/2023 financial year, take responsibilit...
The revelations have sparked concerns over financial accountability and asset management within the ministry, with stakeholders calling for urgent mea...
Forensic audit reveals thousands of workers share bank accounts, salaries are adjusted multiple times in a year, while dismissed employees continue re...
Auditor-General Nancy Gathungu highlighted implementation gaps, mismanagement, and financial shortfalls that could hinder the five main pillars of the...
One of the cases flagged involves the Fisheries Department, where Sh1.6 billion was spent on the Liwatoni tuna fish hub, Sh1.1 billion for constructio...